ABC Heavy Engineering Request a quote

FIELD SERVICES

CompanyABC Heavy Engineering
LocationPaget QLD 4740
Sheetfield services
StandardAS1100 drafting
Crane lowering a red propel gear case onto the Marion 8750 dragline during an on-site change-out, crews in hi-vis on the platform
Fig 01Subject Crane lowering a red propel gear case onto the Marion 8750 dragline d…

Principal contractor on a six week ROM shutdown at BMA Peak Downs, five years of monthly maintenance at Coppabella, LTI free, and the full Paget workshop behind every crew, 24/7.

Two mobile cranes rigged over a Peabody P&H face shovel during a field rebuild, rainbow behind
Fig 02Shows Two mobile cranes rigged over a Peabody P&H face shovel dur…

PRINCIPAL CONTRACTOR, NOT ONLY A LABOUR SUPPLIER

Our Field Division takes construction, shutdown, plant maintenance and breakdown work across the Bowen Basin and beyond. ABC has been principal contractor for a six week ROM shutdown at BMA Peak Downs, and has held five years of monthly maintenance at Coppabella, LTI free.

In situ hoist and drag drum rebuilds and Marion 8750 propel gear case change outs are done on the machine, on your schedule. Every job is backed with the same QA documentation we apply in the shop, so what was measured in the pit is recorded and signed off.

Mobile crane hoisting a large structural component above the Curragh dragline unit 303 on a Bowen Basin mine site
Fig 03Shows Mobile crane hoisting a large structural component above th…

THE PLANT WE WORK ON, AND THE CREWS WE SEND

Field crews bring the full capability of the Paget workshop to your site, 24/7. Where you need people rather than a package, ABC holds a Queensland labour hire licence, LHL-01983-S5B8T, and supplies planners, supervisors, relief personnel and trades.

Crane lowering a red propel gear case onto the Marion 8750 dragline during an on-site change-out, crews in hi-vis on the platform
Fig 04Shows Crane lowering a red propel gear case onto the Marion 8750…
  • Electric draglines & face shovels
  • Hydraulic excavators
  • Coal processing plants
  • Blast hole drill rigs
  • Sugar mills
  • Power stations
  • Shipping (on and offshore)
  • Shutdown & project crews

SCOPE & CAPACITY

Operating envelope, published figures
Shutdowns
Principal contractor, six week ROM shutdown at BMA Peak Downs
Maintenance record
Five years of monthly maintenance at Coppabella, LTI free
In situ rebuilds
Hoist and drag drum rebuilds on the machine
Gear case change outs
Marion 8750 propel gear cases
Labour hire licence
LHL-01983-S5B8T
Labour supplied
Planners, supervisors, relief personnel and trades
Crews
Shutdown and project crews
Availability
24/7, backed by the Paget workshop

RELATED WORK

01Transport & CranesThe float and the Franna that move a change out component to the pad…
02FittingA gear case pulled on site comes back to jacking presses rated to 600…
03Steel Fabrication & WeldingStructural repairs to booms, side frames, car bodies and buckets are…

Put a job in front of us

Send the drawing, the failed component or the breakdown. Seven departments and the field division respond from one complex at Paget.

07 4952 3444 24/7 emergency call out Request a quote